Osborne Mine
Scoping study and capital cost estimate for Site storage building and rail loading facility plus train unloading and conveying, storage and reclamation system for 1 Mtpa magnetite project.
|
BHP Billiton GEMCO
Projects undertaken since 1986 include:
Structural designs, fuel farm upgrade, quarry dewatering, tails dam and decant tower design, dump station upgrades, design of mobile reclaim hopper car, concentrator modifications, conveyor designs and modifications, sand tails disposal procedure, water reclamation from tailings dams,
provision of on site engineer, studies for increased capacity of crusher station.
|
Cape Flattery (Silica)
2 Mtpa raw silica slurry transport pipeline and pumping system. Project including slurry mixing and
storage primary and secondary slurry pumping stations and 6 kilometre slurry pipeline as well as return water pipeline and pumping system.
|
BHP Cannington
Design of paste fill conveyor including belt rotation system. The conveyor is specifically designed to minimise segregation of the cement strengthened paste fill material. The structure is elevated above 1 in 100 year flood levels to meet environmental constraints.
|
Other Projects of Interest:
|
|
|
|