Project Overview
|
 |
 |
 |
Xstrata Coal Prep Plant Upgrade
This was completed in two stages to increase throughput from 650 tph to 1,350 tph and included
the installation of 2 off 110 square metre belt filters.
Project Capital cost was $18M with design throughput achieved within 24 hours of commencement
of commissioning of the third module.
|
 |
 |
|